Improvements Needed to Xcel’s Proposed MN Community Solar Program

Date: 11 Nov 2013 | posted in: Energy, Energy Self Reliant States | 0 Facebooktwitterredditmail

Xcel Energy has published their proposed community solar program on Sept. 30, 2013 and ILSR submitted comments on the unlawfully capped and fee-crazy program last week. Comments below

Public Comments on Community Solar (Docket E-002/M-13-867)

Program Design Requirements

Does Xcel’s proposed plan for operating a community solar garden (CSG) meet all the program design requirements, as well as the terms and conditions in Minn. Stat. §216B.1641? Are there other relevant program design features or terms and conditions required for a successful program?

No.  The 20 MW limit under the proposed plan is clearly against the spirit and letter of the law which requires there to be no limit on the amount of capacity allowed under the community solar program.

Furthermore, even a short-term limit on community solar installations could put them at an economic disadvantage. In the two years they propose limiting community solar, other solar projects will be rushing to interconnect while the utility still needs solar capacity and while the federal 30% tax credit is still available (through December 2016).  Xcel has also clearly indicated an interest (in its filing) in developing utility-scale solar projects (often 20 MW and larger) that may quickly consume available capacity under the solar standard, lessening the value of solar renewable energy certificates (RECs).

In 2012, three U.S. states installed more than 400 MW of solar in that year alone.  Seven states installed at least 100 MW of solar energy.  Community solar should be allowed to grow as much as the market can bear while the solar RECs still have a high value to the utility.

Sufficient Disclosure?

Does Xcel’s plan contain sufficient disclosure and protection for Xcel customers/program subscribers, including the identification of all information that must be provided to potential subscribers to ensure fair disclosure of future costs and benefits of subscriptions?

No comment

Interim Rate Paid

Prior to the establishment of a Value of Solar rate, pursuant to Minn. Stat. §216B164, subd. 10, what should be the interim rate paid to subscribers by Xcel for the purchased energy and transfer of renewable energy credits (RECs)? How long should this interim rate remain in effect?

The interim rate should mimic other community net metering policies by reimbursing the customer (in dollars) for their kilowatt-hour production times the retail rate they pay for energy.

If Xcel wishes to offer producers an option to sign a long-term purchase contract for energy (similar to the value of solar tariff), it should reflect the expected present value of the payments that would be received under the above rate, and at a comparable low-risk interest rate for the contract life (e.g. U.S. Treasuries).

Xcel’s retail electricity rates have risen nearly 40% in the past decade and the utility has announced its intention to increase rates in each of the next four years.  If allowed to compel community solar subscribers to accept a long-term, flat rate payment, Xcel would put them at a severe disadvantage to traditional net metering customers, an unlikely legislative intent.

Rapidly rising electricity rates in Minnesota

Transfer of RECs should follow existing state policy.  Under net metering, Xcel does not retain ownership of the renewable energy credits.  Despite significant revisions to the net metering statute by the 2013 legislature, the lack of change indicates intent to maintain this policy, even as the legislature clearly intended the REC to transfer under a value of solar tariff.  Furthermore, the value of solar tariff has a clearly outlined methodology for allowing the solar energy producer to capture the full value of their solar energy, including the REC.  The net metering policy does not similarly reflect a utility payment for the REC.

Reasonable Implementation Schedule?

Is the implementation schedule for the CSG program included in Xcel’s plan reasonable and consistent with the public interest?

Absolutely not.

As mentioned previously and in direct contradiction to the utility’s claim, the two-year program cap is no different from a total program cap, clearly prohibited by state law. An artificial cap on the community solar program puts it at a competitive disadvantage to other forms of solar ownership, including utility-owned solar energy, because REC values may be depressed within two years.

The cap on community solar may also act to increase the cost of solar energy acquired by community solar projects.  The 30% federal tax credit expires in December 2016.  It is in the financial interest of Xcel ratepayers to maximize the amount of solar energy projects receiving this incentive.  But the cap on community solar projects through 2015 will leave little time to capture the incentive if there’s far more demand than Xcel’s unlawful cap allows.

The proposed two-year cap on community solar projects may also increase the risk to subscribers by encouraging overly hasty development.   With an artificial and very limited capacity available, community solar developers will hasten to get their projects in the queue before the quarterly or annual cap is met.  This haste could lead to poorly planned projects.

Interconnection Costs

Is the proposed mechanism that allows Xcel to recover interconnection costs for each community solar garden fair and reasonable?

No comment

Promotions

Are the means by which Xcel proposes to promote its CSG program sufficient?

No comment

Reasonable Application Process?

Is Xcel’s proposal for an application and approval process reasonable?

No.

First-come, first-served application deadlines favor larger solar developers who have in-house legal and financing expertise with significant experience in utility application processes.  With its feed-in tariff program, Los Angeles helped to level the playing field by treating all applications received within a 5-day window equally, and using a lottery to select winning projects.

The utility could also use an initial point screening of applications, filtering out applications for projects that lack ownership or lease access to the proposed project location. Ontario goes further, and its point system for standard offer projects gives priority to projects that have a higher portion of local ownership, are owned or sited on public property, or that have a resolution of support from the host municipality. Priority could also be granted for projects that have a greater relative economic development impact, such as those that use financing from Minnesota-based lenders or made in Minnesota solar equipment.

Reasonable Fees?

Are Xcel’s proposed Consumer Solar Garden Operator deposits and fees fair and reasonable? 

No. Xcel has more and more expensive application fees than many other comparable programs around the country and the fees are very burdensome especially for small community solar projects.

Xcel’s application fee is high compared to other standard offer programs supporting similarly sized projects, especially in the context of its other very high fees.

  • Ontario’s feed-in tariff  ($500)
  • Los Angeles feed-in tariff  ($500 or $1000)
  • Consumers Energy Experimental Advanced Renewables Program ($0)
  • Vermont’s standard offer program ($200)
  • Gainesville solar feed-in tariff ($1200)

None of the above programs have annual fees or monthly metering fees. Xcel’s proposed fee is unique and expensive, equivalent to a 4% annual tax on production for a 50 kW community solar project.

Xcel’s security deposit and escrow (a combined $200 per kW) greatly exceeds of those required by other community solar or standard offer programs:

  • Ontario’s feed-in tariff  ($5 per kW for community projects)
  • Los Angeles feed-in tariff  ($50 per kW AC)
  • Consumers Energy Experimental Advanced Renewables Program ($0)
  • Vermont’s standard offer program ($15 per kW).
  • Gainesville solar feed-in tariff ($30 per kW)

One must ask whether program fees are necessary at all.  Massachusetts, which requires utilities to offer virtual net metering to support community solar projects, treats it no different from traditional net metering.  Utilities are forbidden from charging extra fees to net metered projects, community or otherwise.

Xcel Energy excessive community solar fees Minnesota 2013

Other Issues

Mapping Distribution System Capacity

Inexplicably, Xcel says they have no plans to produce a publicly accessible map of capacity on their distribution system.  Why not? As shown in the stakeholder discussion on value of solar, location of solar projects can make a difference in its value to the distribution grid, the utility, and ratepayers.

Such a map would help direct the development of solar energy projects into areas with existing grid capacity and with low upgrade needs.  Xcel could even use the map to direct installations (particularly community solar, which has geographic flexibility) toward areas where the distribution capacity deferral opportunity is the greatest.  The Long Island Power Authority is paying solar projects in strategic geographic areas up to 7¢ per kilowatt-hour more for energy. Even if the locational premium is not nearly as high, refusing to help developers produce energy in areas of strategic significance would be a missed opportunity.

Facebooktwitterredditmail
Avatar photo
Follow John Farrell:
John Farrell

John Farrell directs the Energy Democracy initiative at the Institute for Local Self-Reliance and he develops tools that allow communities to take charge of their energy future, and pursue the maximum economic benefits of the transition to 100% renewable power.